This City of Portland, Oregon project involved a two-lane tunnel 250 feet long and another 500 feet long. Each tunnel

Cornell Tunnel Repairs

This City of Portland, Oregon project involved a two-lane tunnel 250 feet long and another 500 feet long. Each tunnel received a new illumination system; hydro demolition removal of delaminated and deteriorated concrete; installation of approximately 120 cubic yards of new shotcrete lining; drainage improvements behind the new lining and the existing concrete. This drainage included 3-inch diameter drain holes drilled 10 feet deep into the hillside. In total, 20 cubic yards of voids were pressure grouted.

Location

Independence, Oregon

Start

September 2010

Completion Date

March 2011

Owner

Oregon Department of Transportation

Year

2013