This project involves constructing bridge strengthening; traffic control; installing new guardrails and constructing guardrail flares; and installing unique pavement markings. The bridge strengthening consists of repairing bridge deck concrete; epoxy injection crack sealing; installing internal shear anchors; and installing new titanium alloy reinforcement embedded into the girders. Other work included in this project was pavement removal and new asphalt paving, and pavement striping.
Mosier, Oregon
April 2014
June 2014
Oregon Department of Transportation
2013