This project repaired approximately 1/2 mile of SR 2. The scope involved removing spalled concrete, abrasive blasting

State Route 2 Bridge Rehabilitation

Milepost .64 to 1.20

This project repaired approximately 1/2 mile of SR 2. The scope involved removing spalled concrete, abrasive blasting, rebar repairs, watertight formwork, pressure grouting voids/repair areas, applying carbon fiber reinforcement, and applying pigmented sealer. Most of the work was constructed at night to minimize disruption to the approximately 250,000 vehicles per day.

Location

Everett, Washington

Start

April 2011

Completion Date

September 2011

Owner

Washington State Department of Transportation

Year

2013