Project Description
This project removed an old wood stop log spillway system and upgraded it to hydraulically controlled Obermeyer sluice gates. Major hydro-demo on the sloped spillway system was required to provide channels for the control lines, both horizontal and vertical. We had to build extensive heavy-duty scaffolding to access the demo and control installation areas. This scaffolding provided worker access, the hydro-demo machine, and a landing spot for copious amounts of concrete deposits for removal. An added scope to the project was the construction of the control building and equipment. A major flooding event occurred during this project’s final stages, which not only shut it down for several months but also caused extensive damage to the scaffolding.
Project Team and Stats
- Location: Oregon City, OR
- Start Date: July 2016
- Completion Date: Weather Delay
- Owner: Portland General Electric